CAPTION
Ratification of the fully executed Change Order No.2, reflecting an increase in the amount of $22,400.00 and additional forty-five (45) calendar days for the project ''Southwest Weslaco -2018 Bond Referendum Project No. 35 '', Contract No. (C-HCDD1-23-056-11-14), with Mor-Wil, LLC, as recommended by Project Engineer, Omar Anzaldua Jr., PE, CFM, PMP, CCM, and as approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM