AI- 95736
Purchasing Department 14.D.2.
CC CONSENT AGENDA SPECIAL MTG
Prct. 4
- Meeting Date:
- 06/20/2024
- Submitted For:
- Ignacio Amezcua
- Submitted By:
- Victor Borrego
- Department:
- PURCHASING DEPT.
Information
CAPTION
Requesting acceptance and approval of Change Order No.2 from RDH Site and Concrete, LLC for the "Hidalgo County Precinct 4 Construction for Mile 17 Rd Stormwater Project" (C-22-0087-08-22-10), for a 30-day time extension and total project increase of $11,417.50, as recommended by the Project Engineer, L&G Consulting Engineers, Inc.
BACKGROUND
Fiscal Impact
- CALENDAR YEAR:
- 2024
- ACCT. #:
- 4-1290-431-50-115-242-4-723
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Funds available; PO #870199Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | Ignacio Amezcua | 06/14/2024 01:58 PM |
| Budget and Management | Veronica Ortiz | 06/14/2024 02:09 PM |
| Final Approval | Monica Salinas | 06/14/2024 05:18 PM |
- Form Started By:
- Victor Borrego
- Started On:
- 06/13/2024 04:34 PM
- Final Approval Date:
- 06/14/2024