AI - 95770
6.C.
DD-REGULAR AGENDA SPECIAL MTG
- Meeting Date:
- 06/20/2024
- Submitted For:
- Yvette Barrera
- Submitted By:
- Enriqueta Zambrano
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Requesting approval of Change Order No.4, reflecting an increase in the amount of $180,557.75, and Ninety (90) additional calendar days, in connection with the project "South ''I'' Rd USIBWC Structure 82L Drainage Improvements -2018 Bond Referendum Project No. 33’', Contract No. C-HCDD1-22-060-11-29, with Mor-Wil, LLC, as recommended by Project Engineer, Assistant General Manager, Omar Anzaldua, Jr., PE, CFM
BACKGROUND
Fiscal Impact
Attachments
No file(s) attached.