Jackson Rd Phase 2 - Bond 516
1. Approval of Application for Payment No. 4 in the amount of $11,358.00 from RDH Site and Concrete, LLC pertaining to Construction Contract C-HCDD1-21-047-11-30 Jackson Rd Phase 2. Project Engineer Quintanilla Headley PO#648343

2. Approval and acceptance of Certificate of Substantial Completion and Certificate of Construction Completion from RDH Site and Concrete, LLC pertaining to Construction Contract C-HCDD1-21-047-11-30 Jackson Rd Phase 2. Project Engineer Quintanilla Headley PO#648343

3. Approval of Application for Payment No. 5 Retainage in the amount of $47,108.80 and $280.70 in interest from RDH Site and Concrete, LLC pertaining to Construction Contract C-HCDD1-21-047-11-30 Jackson Rd Phase 2. Project Engineer Quintanilla Headley PO#648343

Southwest Weslaco - Budget 535
4. Approval of Application for Payment No. 4 in the amount of $113,816.36 from Mor-Wil, LLC pertaining to Construction Contract C-HCDD1-23-056-11-14 Southwest Weslaco. Project Engineer HCDD1 Omar Anzaldua, Jr. PE, CFM PO#648668

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 09/20/2024 04:14 PM
Form Started By:
Alvaro Chuc
Started On:
09/20/2024 09:58 AM
Final Approval Date:
09/20/2024