Information
CAPTION
Requesting approval of Change Order No. 2, reflecting an increase in the amount of $95,253.44 and 121 additional construction calendar days for the project “South Main Drain Channel Improvements Project Phase I 2023 Bond Project No. 3", Contract No. C-HCDD1-23-053-10-31, with RG Enterprises, LLC dba G&G Contractors, as recommended by Project Engineer, Assistant District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM