AI - 98412
8.B.
DD-REGULAR AGENDA SPECIAL MTG
- Meeting Date:
- 02/18/2025
- Submitted For:
- Yvette Barrera
- Submitted By:
- Enriqueta Zambrano
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Requesting approval of Change Order No. 2, reflecting an increase in the amount of $72,017.87 and 261 additional construction calendar days for the project ''South I Rd East Side Drainage Improvements -2018 Bond Referendum Project No. 33'', Contract No. C-HCDD1-22-029A-08-09, with RBM Contractors, LLC, as recommended by Project Engineer, B2Z Engineering LLC.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 02/14/2025 04:05 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 02/13/2025 11:05 AM
- Final Approval Date:
- 02/14/2025