AI - 98582
8.B.
DD-REGULAR AGENDA SPECIAL MTG
- Meeting Date:
- 03/04/2025
- Submitted For:
- Omar Anzaldua Jr.
- Submitted By:
- Enriqueta Zambrano
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Requesting approval of Change Order No.1, reflecting an increase in the amount of $88,464.50 and 60 additional construction calendar days for the project ''Pharr-McAllen Lateral East - 2023 Bond Referendum Project No. 9'', Contract No. C-HCDD1-24-029-06-11, with Synergy Development & Construction, LLC, as recommended by Project Engineer, GDJ Engineering LLC.
BACKGROUND
1. To install 5" Concrete Rip-Rap on the North side of the existing ditch to prevent erosion at the outfall.
2. Additional 60 days to complete the Rip-Rap
3. Project end date for this change order: April 29, 2025
At the request of the Hidalgo County Drainage District No. 1
2. Additional 60 days to complete the Rip-Rap
3. Project end date for this change order: April 29, 2025
At the request of the Hidalgo County Drainage District No. 1
Fiscal Impact
- CALENDAR YEAR:
- 2025
- ACCOUNT #:
- 25-173-433-709-47330-020-301
- FUNDS AVAILABLE? Y/N:
- Y
- MATCHING FUNDS? Y/N:
BUDGETARY IMPACT:
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 02/28/2025 04:35 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 02/27/2025 01:46 PM
- Final Approval Date:
- 02/28/2025