AI - 98650
4.A.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 03/18/2025
- Submitted For:
- Yvette Barrera
- Submitted By:
- Enriqueta Zambrano
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of the fully executed Change Order No.3, reflecting an increase in the amount of $24,927.40 and an additional forty-five (45) calendar days for the project ''Southwest Weslaco -2018 Bond Referendum Project No. 35 '', Contract No. C-HCDD1-23-056-11-14, with Mor-Wil, LLC, as recommended by Project Engineer, Omar Anzaldua Jr., PE, CFM, PMP, CCM, and as approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM
BACKGROUND
CO-3: Project end date 1-25-2025
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 03/14/2025 03:55 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 03/07/2025 09:12 AM
- Final Approval Date:
- 03/14/2025