AI - 99095
4.C.
DD-CONSENT AGENDA SPECIAL MTG
Meeting Date:
04/15/2025
Submitted For:
Omar Anzaldua Jr.
Submitted By:
Justin Silva
Department:
DRAINAGE DISTRICT

Information

CAPTION

Ratification of approved and fully executed Change Order No.1, reflecting 62 additional days for the project ''Mission McAllen Drain Phase 3 - 2023 Bond Project No. 12'', Contract No. C-HCDD1-24-032-07-09, with Synergy Development & Construction, LLC., as recommended by Project Engineer, SAMES, Inc and approved by District General Manager, Raul E. Sesin, PE, CFM