Skip to main content

AgendaQuick™

View Agenda Item

AI- 99372
Planning Department   3.D.
CC CONSENT AGENDA SPECIAL MTG
Meeting Date:
05/13/2025
Submitted For:
Flor Castillo
Submitted By:
Flor Castillo
Department:
PLANNING DEPT.

Information

CAPTION

1. PIPELINE PERMITS 
a. Applicant: Housley Group FTR# 5314105 Pct. 1
Proposed improvement within Right-of-Way: A new fiber optic cable measuring 1 1/2” is to be installed within the right of way of Palos Nuevos Drive, Palos Ricos Drive, and Mile 4 West Road; Palos Rojos #2 Subdivision.   
 A new fiber optic cable measuring 1 1/2” is to be installed within the right of way of Marin Street, Salinas Street, Colosio Street, Mile 12 North Road, and Mile 4 West Road; Palos Verdes #1 Subdivision. 
 
A new fiber optic cable measuring 1 1/2” is to be installed within the right of way of the north east corner of Mile 4 West Road and Milr 12 north Road; Wingston Commercial Subdivision.
 
A new fiber optic cable measuring 1 1/2” is to be installed within the right of way of De La Madrid Street, Mile 12 North Road, and Portillo Circle; Palos Blancos Unit B Subdivision
 
A new fiber optic cable measuring 1 1/2” is to be installed within the right of way of Mile 12 North Road, Mkle 4 ½ West Road, Fox Street, Cortez Street, Ruiz Street, Colosio Circle; Palos Blancos Unit A Subdivision.
 
A new fiber optic cable measuring 1 1/2” is to be installed within the right of way of the south west corner of Mile 12 North Road and Mile 4 ½ West Road; Jaime Subdivision.

b. Applicant: Housley Group FTR# 5314107 Pct. 1
Proposed improvement within Right-of-Way: A new fiber optic cable measuring 1 1/2” is to be installed within the right of way of Mile 6 ½ West Road, El Sol Drive, Pueblo Del Sol West Street, Mi Tierra Drive, Mi Cielo Drive, Mis Padres Drive,  Las Nubes Drive, Las Estrellas Drive; Pueblo Del Sol Subdivision.   

c. Applicant: Vexus Fiber EDBG 02-0106 -Pct. 4
Proposed improvement within Right-of-Way: A new fiber optic cable measuring 1 1/2” is to be installed along Alamo Road, Falcon Crest Lane, Pelegrine Drive, Pigeon Drive, Kestrel Drive, Mauritius Lane; Falcon Crest Gardens Subdivision.
 
A new fiber optic cable measuring 1 1/2” is to be installed within the right of way of San Roman Terrace, Pelegrine Drive, San Diego Drive, Kestrel Drive; Hacienda San Roman Ph. 1 Subdivision.
 
A new fiber optic cable measuring 1 1/2” is to be installed within the right of way of Richardson Road, Terry Road, Serna Drive, Sunrise Circle; Towne East Unit 1 Subdivision.
 
A new fiber optic cable measuring 1 1/2” is to be installed within the right of way of Terry Road and Jax Road; Jackson New World Development Unit 2 Subdivision.
 
A new fiber optic cable measuring 1 1/2” is to be installed within the right of way of Jaguar Drive, Terry Road, Cumbia Street, Celebrity Street, Nominee Street; Selena Heights Ph. 1 Subdivision.
 
A new fiber optic cable measuring 1 1/2” is to be installed within the right of way of Mile 17 North Road, Terry Road; Slots Drive, Black Jack Street, Bacarret Street, Roulette Street; Monte Carlos EstateSubdivision.
 
A new fiber optic cable measuring 1 1/2” is to be installed within the right of way of Mile 17 North Road, Enron Street; Pipeline Estates Subdivision.

d. Applicant: Vexus Fiber EDBG 06-002 -Pct. 3
Proposed improvement within Right-of-Way: A new fiber optic cable measuring 1 1/2” is to be installed along north northeast corner of Glasscock Road and Mile 6 Road.

e. Applicant: Housley Group FTR# 5314121 Pct. 1
Proposed improvement within Right-of-Way: A new fiber optic cable measuring 1 1/2” is to be installed within the right of way of Sugar Cane Drive, Granada Drive, Suarez Drive; Suarez Subdivision, Delta Corts Subdivision.
 
A new fiber optic cable measuring 1 1/2” is to be installed within the right of way of Mile 6 ½ West Road, Melissa Drive, Alvarez Street, Flores Street, Kerps Street; Barbosa Lopez Unit 3, and Guadalupe Subdivision.

f. Applicant: Vexus Fiber EDBG 06-013 -Pct. 3
Proposed improvement within Right-of-Way: A new fiber optic cable measuring 1 1/2” is to be installed along Taylor Road running ½ mile north from Auburn Avenue.  
 
g. Applicant: North Alamo Supply Corporation
Legal Description: Lot 1 Survey 3 RB Curry Survey (Tex-Mex Road & FM 1423) (Pct. 4)
Location of Pipeline or Utilities: Existing 6” waterline north of Tex Mex Road.
Proposed improvement within Right-of-Way: One 3/4” water service line with a 2” PVC casing boring Tex Mex Road. 

h. Applicant: North Alamo Supply Corporation
Legal Description: 4.88 acres out of Blk. 122 La Blanca Ag. Co. Subdivision; OTI Subdivision Ph. 1 (FM 493 & Mile 13 ½ North Road) (Pct. 1)
Location of Pipeline or Utilities: Existing 6” waterline south of Mile 13 ½ North Road.
Proposed improvement within Right-of-Way: Two 1” dual water service lines with a 2” PVC casing boring Mile 13 ½ North Road. 

i. Applicant: Brush Country Construction
Legal Description: 11.34 acres out of Farm tract 99 San Salvador Del Tule Grant Subdivision (FM 3250 & Floral Road) (Pct. 4)
Location of Pipeline or Utilities: Existing 8” waterline north of Floral Road.
Proposed improvement within Right-of-Way: One 3/4” water service line with a 2” PVC casing boring Floral Road. 

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Budget and Management Veronica Ortiz 05/08/2025 08:35 AM
Final Approval Monica Salinas 05/09/2025 05:40 PM
Form Started By:
Flor Castillo
Started On:
05/08/2025 08:25 AM
Final Approval Date:
05/09/2025