Ratification of approved and fully executed Change Order No.1, reflecting an increase in the amount of $23,025.00 and an additional 40 construction calendar days for the project ''Anaquitas Drainage Improvements Project Phase 2 -2018 Bond Referendum Project No. 8'', Contract No. C-HCDD1-25-006-02-18, with Gonzalez Engineering & Management, LLC, as recommended by Project Engineer, B2Z Engineering LLC and approved by District General Manager, Raul E. Sesin, PE, CFM.

BACKGROUND

Project end date for Change Order 1: December 11, 2025