CAPTION

Ratification of approved and fully executed Change Order No.1, reflecting 25 additional calendar days for the project ''Southwest Weslaco Ph III-A IBWC Structure 105AL -2018 Bond Referendum Project No. 35'', Contract No. (C-HCDD1-24-055-11-12), with Mor-Wil, LLC, as recommended by Project Engineer, S2 Engineering, PLLC and approved by District General Manager, Raul E. Sesin, PE, CFM.

BACKGROUND

End Date for change order 1 - September 21, 2025

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 08/15/2025 02:33 PM
Form Started By:
Enriqueta Zambrano
Started On:
08/11/2025 11:05 AM
Final Approval Date:
08/15/2025