AI- 100884
Purchasing Department   13.D.2.
CC CONSENT AGENDA SPECIAL MTG
Prct. 2
Meeting Date:
09/30/2025
Submitted For:
Eddie Cantu
Submitted By:
Lupita Garza
Department:
COMM. PCT. #2

Information

CAPTION

Requesting approval of Application for Payment No. 1 in the amount of $58,685.77 for Pct. 2 Recreational Trails Connectivity Project Mission Segment 1 (ARPA-21-122-040) submitted by the contractor, Urbe 21 Design & Construction, LLC (Contract C-25-0170-05-13) and reviewed by the Project Manager, Julian Ibarra.

BACKGROUND


Fiscal Impact

CALENDAR YEAR:
2025
ACCT. #:
5-1301-126-30-122-177-1-000
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Funding is available through PO#900388 in the amount of $823,832.94 as of 09/17/25. Partial payment will be issued from the due from Mission Account for their committed ICA contribution.

CALENDAR YEAR:
2025
ACCT. #:
5-1290-452-67-115-233-2-740
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

N/A

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal Ignacio Amezcua 09/23/2025 03:36 PM
Budget and Management Veronica Ortiz 09/23/2025 03:47 PM
Final Approval Monica Salinas 09/24/2025 04:42 PM
Form Started By:
Lupita Garza
Started On:
09/17/2025 03:22 PM
Final Approval Date:
09/24/2025