CAPTION

West Main Drain Phase 3 - Budget 703
1. Approval of Application for Payment No. 2 in the amount of $250,732.08 from Renoworks pertaining to Construction Contract C-HCDD1-24-059-11-13 West Main Drain 3 Phase 3. Project Engineer Javier Hinojosa, PO#650336

Mission McAllen Drain - Budget 712
2. Approval and acceptance of Certificate of Substantial Completion and Certificate of Construction Completion from Synergy Development & Construction pertaining to Construction Contract C-HCDD1-24-032-07-09 Mission McAllen Drain. Project Engineer SAMES PO#649764

3. Approval of Application for Payment No. 7 Final in the amount of $109,966.79 and 477.82 in interest (pursuant to Texas Water Code 49.247) from Synergy Development & Construction pertaining to Construction Contract C-HCDD1-24-032-07-09 Mission McAllen Drain. Project Engineer SAMES PO#649764

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 09/24/2025 04:46 PM
Form Started By:
Alvaro Chuc
Started On:
09/23/2025 03:27 PM
Final Approval Date:
09/24/2025