AI - 100870
5.A.
DD-CONSENT AGENDA SPECIAL MTG
Meeting Date:
09/23/2025
Submitted For:
Omar Anzaldua Jr.
Submitted By:
Justin Silva
Department:
DRAINAGE DISTRICT

Information

CAPTION

Ratification of approved and fully executed Change Order No. 1, reflecting an increase in the amount of $12,650.61 and an additional 21 construction calendar days for the project ''Pharr - McAllen Lateral West - 2023 Bond Referendum Project No. 9'', Contract No. C-HCDD1-25-013-04-15, with Construx Enterprises, LLC, as recommended by Project Engineer Izaguirre Engineering Group, LLC, and approved by District General Manager, Raul Sesin, PE, CFM.