AI - 102718
5.B.
DD-CONSENT AGENDA SPECIAL MTG
Meeting Date:
03/17/2026
Submitted For:
Omar Anzaldua Jr.
Submitted By:
Justin Silva
Department:
DRAINAGE DISTRICT

Information

CAPTION

Ratification of approved and fully executed Change Order No.1, reflecting an increase in the amount of $17,612.00 and an additional 181 construction calendar days for the project ''West Main Drain III Phase 1 -2023 Bond Referendum Project No. 14'', Contract No. C-HCDD1-24-061-12-17, with Econ Group, LLC, as recommended by Project Engineer, Assistant District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM and approved by District General Manager, Raul E. Sesin, PE, CFM.