AI - 102751
4.A.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 03/17/2026
- Submitted For:
- Yvette Barrera
- Submitted By:
- Justin Silva
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of approved and fully executed Change Order No.1, reflecting 144 additional days for the project ''Montecristo and Conway Drain Phase III - 2018 Bond Project No. 27'', Contract No. C-HCDD1-25-021-05-29, with Gonzalez Engineering & Management, LLC., as recommended by Project Engineer, B2Z Engineering LLC and approved by District General Manager, Raul E. Sesin, PE, CFM.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 03/11/2026 02:50 PM |
- Form Started By:
- Justin Silva
- Started On:
- 03/10/2026 08:32 AM
- Final Approval Date:
- 03/11/2026