CAPTION
Phase 1 Flood Control Segment 21 - Budget 521
Approval of Application for Payment No. 2 in the amount of $100,980.00 from Gonzalez Engineering & Management pertaining to Construction Contract C-HCDD1-25-029-06-10 Phase 1 Flood Control Segment 21. Project Engineer Javier Hinojosa PO#651664
Approval of Application for Payment No. 2 in the amount of $100,980.00 from Gonzalez Engineering & Management pertaining to Construction Contract C-HCDD1-25-029-06-10 Phase 1 Flood Control Segment 21. Project Engineer Javier Hinojosa PO#651664