AI - 104081
6.A.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 07/21/2026
- Submitted For:
- Omar Anzaldua Jr.
- Submitted By:
- Justin Silva
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of approved and fully executed Change Order No.1, reflecting an increase in the amount of $2,750.00 for the project ''Mission-McAllen Drain Phase IV - 2023 Bond Referendum Project No. 12'', Contract No. C-HCDD1-25-038-10-28, with Econ Group, LLC, as recommended by Project Engineer, Quintanilla Headley & Associates, Inc and approved by District General Manager, Raul E. Sesin, PE, CFM
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 07/15/2026 03:32 PM |
- Form Started By:
- Justin Silva
- Started On:
- 07/14/2026 01:20 PM
- Final Approval Date:
- 07/15/2026