CAPTION
Mayberry - Glasscock Phase 1 - Budget 543
Approval of Application for Payment No. 3 in the amount of $92,989.52 from Venser Construction LLC pertaining to Construction Contract C-HCDD1-25-050-11-10. Project Engineer Javier Hinojosa Engineering PO#651828-R
Approval of Application for Payment No. 3 in the amount of $92,989.52 from Venser Construction LLC pertaining to Construction Contract C-HCDD1-25-050-11-10. Project Engineer Javier Hinojosa Engineering PO#651828-R
BACKGROUND
Fiscal Impact
Attachments