CAPTION
Requesting approval of Change Order No. 4, reflecting an increase of $70,587.50 and 90 additional construction calendar days for the project "PD Lateral Extension 5 –2023 Bond Referendum Project No. 15", Contract No. C-HCDD1-25-015-06-24, with Synergy Development & Construction, LLC, as recommended by Project Engineer, Assistant District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM.