AI - 100762
7.D.
DD-REGULAR AGENDA SPECIAL MTG
- Meeting Date:
- 09/16/2025
- Submitted By:
- Alvaro Chuc
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Anaquitas - Budget 508
Approval of Application for Payment No. 2 in the amount of $226,991.25 from Gonzalez Engineering pertaining to Construction Contract C-HCDD1-25-006-02-18 Anaquitas Phase 2. Project Engineer L&G Engineering PO#650692
Hidalgo Drain - Budget 513
Approval of Application for Payment No. 5 in the amount of $283,344.71 from RDH Site & Concrete, LLC pertaining to Construction Contract C-HCDD1-24-034-08-06 Hidalgo Drain. Project Engineer SAMES Engineering PO#649905 & 649906
Approval of Application for Payment No. 2 in the amount of $226,991.25 from Gonzalez Engineering pertaining to Construction Contract C-HCDD1-25-006-02-18 Anaquitas Phase 2. Project Engineer L&G Engineering PO#650692
Hidalgo Drain - Budget 513
Approval of Application for Payment No. 5 in the amount of $283,344.71 from RDH Site & Concrete, LLC pertaining to Construction Contract C-HCDD1-24-034-08-06 Hidalgo Drain. Project Engineer SAMES Engineering PO#649905 & 649906
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 09/10/2025 02:30 PM |
- Form Started By:
- Alvaro Chuc
- Started On:
- 09/09/2025 01:11 PM
- Final Approval Date:
- 09/10/2025