AI- 101016
Purchasing Department   13.E.4.
CC CONSENT AGENDA SPECIAL MTG
Prct. 4
Meeting Date:
10/14/2025
Submitted For:
Ignacio Amezcua
Submitted By:
Cassandra Carr
Department:
PURCHASING DEPT.

Information

CAPTION

Requesting acceptance and approval of Change Order No. 2 from Saenz Brothers Construction, LLC, for the "J-01 Stormwater Management Project" (C-24-0337-10-29) to reflect an additional 120 calendar days beyond the original contract completion date, as recommended by the Engineering firm TEDSI Infrastructure Group.

BACKGROUND

Unforeseen utility conflict with Vexus (new install) on March 19, 2025. Operations halted for redesign.

Fiscal Impact

CALENDAR YEAR:
2025
ACCT. #:
5-1200-431-00-124-007-0-723
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Funds available as of 9/30/2025.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal Ignacio Amezcua 10/03/2025 02:53 PM
Budget and Management Melannie Rivera 10/03/2025 02:56 PM
Final Approval Monica Salinas 10/07/2025 02:49 PM
Form Started By:
Cassandra Carr
Started On:
09/30/2025 04:20 PM
Final Approval Date:
10/07/2025