AI- 101465
Purchasing Department 25.E.1.
CC REGULAR AGENDA SPECIAL MTG
Prct. 4
- Meeting Date:
- 11/10/2025
- Submitted For:
- Ignacio Amezcua
- Submitted By:
- Hector Garcia
- Department:
- PURCHASING DEPT.
CAPTION
A. Requesting acceptance and approval of Change Order No. 6 from RG Enterprises dba G&G Contractors, for the Construction of Hidalgo County Pct. 4 All-Star Park (C-21-0832-02-11), to address a reduction in the scope of work and liquidated damages that will be deducted from retainage, for $147,069.56; as recommended by the Project Architect, The Warren Group Architects, Inc.
B. Requesting acceptance and approval of the Certificate of Construction Completion from RG Enterprises dba G&G Contractors for the "Construction of Hidalgo County Precinct No.4 All-Star Park" project, along with final payment of $34,312.57, with authority for the County Judge to sign all required documentation.
B. Requesting acceptance and approval of the Certificate of Construction Completion from RG Enterprises dba G&G Contractors for the "Construction of Hidalgo County Precinct No.4 All-Star Park" project, along with final payment of $34,312.57, with authority for the County Judge to sign all required documentation.
BACKGROUND
Fiscal Impact
- CALENDAR YEAR:
- 2025
- ACCT. #:
- 5-1357-452-00-124-132-0-740
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
- CALENDAR YEAR:
- 2025
- ACCT. #:
- 5-1303-452-00-124-132-0-740
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | Ignacio Amezcua | 11/04/2025 04:51 PM |
| Budget and Management | Veronica Ortiz | 11/04/2025 04:52 PM |
| Final Approval | Monica Salinas | 11/04/2025 04:57 PM |
- Form Started By:
- Hector Garcia
- Started On:
- 11/04/2025 04:11 PM
- Final Approval Date:
- 11/04/2025