CAPTION
Ratification of approved and fully executed Change Order No.3, reflecting an increase in the amount of $13,844.00 and 80 additional calendar days for the project ''PSJA Drain (Expwy 83 to Earling Rd) -2023 Bond Referendum Project No. 16'', Contract No. (C-HCDD1-24-056-10-29), with Clore Equipment, LLC, as recommended by Project Engineer, Assistant District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM and approved by District General Manager, Raul E. Sesin, PE, CFM.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 02/10/2026 01:54 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 01/30/2026 08:24 AM
- Final Approval Date:
- 02/10/2026