Ratification of approved and fully executed Change Order No. 2, reflecting an increase in the amount of $21,086.96 and an additional 61 construction calendar days for the project ''Pharr - McAllen Lateral West - 2023 Bond Referendum Project No. 9'', Contract No. C-HCDD1-25-013-04-15, with Construx Enterprises, LLC, as recommended by Project Engineer Izaguirre Engineering Group, LLC, and approved by District General Manager, Raul Sesin, PE, CFM.