CAPTION
Ratification of the approved and fully executed Change Order No. 6, reflecting a decrease in the amount of ($40,166.89) and 103 additional days for the project ''South Main Drain Channel Improvements Project Phase I -2023 Bond Referendum Project No. 3'', Contract No. C-HCDD1-23-053-10-31, with RG Enterprises, LLC dba G&G Contractors., as recommended by Project Engineer Assistant District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM and approved by District General Manager, Raul E. Sesin, PE, CFM.