Skip to main content

AgendaQuick™

View Agenda Item

AI - 103166
3.A.
DD-CONSENT AGENDA REGULAR MTG
Meeting Date:
04/28/2026
Submitted For:
Omar Anzaldua Jr.
Submitted By:
Justin Silva
Department:
DRAINAGE DISTRICT

CAPTION

Ratification of the approved and fully executed Change Order No. 6, reflecting a decrease in the amount of ($40,166.89) and 103 additional days for the project ''South Main Drain Channel Improvements Project Phase I -2023 Bond Referendum Project No. 3'', Contract No. C-HCDD1-23-053-10-31, with RG Enterprises, LLC dba G&G Contractors., as recommended by Project Engineer Assistant District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM  and approved by District General Manager, Raul E. Sesin, PE, CFM.

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 04/22/2026 02:54 PM
Form Started By:
Justin Silva
Started On:
04/16/2026 03:02 PM
Final Approval Date:
04/22/2026