AI- 103479
Purchasing Department 19.B.2.
CC REGULAR AGENDA REGULAR MTG
Prct. 2
- Meeting Date:
- 05/26/2026
- Submitted For:
- Ignacio Amezcua
- Submitted By:
- Juan Herrera
- Department:
- PURCHASING DEPT.
CAPTION
Requesting acceptance and approval of Change Order No. 4 from RGV Construction, LLC, for the "[ARPA-24-340-352] - Construction Manager at Risk for McAllen Health Center Improvement Project" (C-24-0312-09-27), for additional scope in the amount of $107,072.70, as recommended by the Project Manager, B2Z Engineering, LLC.
BACKGROUND
24-0312-COR(04)
Project String: E-1150035200-GRANT-PUBLC HLTH-BUILDINGS
Project String: E-1150035200-GRANT-PUBLC HLTH-BUILDINGS
Fiscal Impact
- CALENDAR YEAR:
- 2026
- ACCT. #:
- 1290-41-115-000-0000-507300
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- Y
BUDGETARY IMPACT:
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | Ignacio Amezcua | 05/18/2026 05:03 PM |
| Budget and Management | Veronica Ortiz | 05/19/2026 11:25 AM |
| Final Approval | Monica Salinas | 05/19/2026 04:40 PM |
- Form Started By:
- Juan Herrera
- Started On:
- 05/15/2026 08:32 AM
- Final Approval Date:
- 05/19/2026