CAPTION

TDEM North Main Drain Phase 2 - Budget 204
Approval of Application for Payment No. 5 in the amount of $65,148.41 from Clore Equipment LLC pertaining to Construction Contract C-HCDD1-25-063-03-03. Project Engineer HCDD1 Omar Anzaldua, Jr., PE, CFM PO#652180