CAPTION
Requesting approval of Change Order No. 2 (C-25-0169-05-13) with RBM Contractors, LLC for the Hidalgo County Precinct #2 — Recreational Trails Connectivity Project — McAllen Segment 1 (from Taylor Rd. to Ware Rd. and 23rd St. to 10th St.), as recommended by Project Manager Saul Ramos, with authority for Commissioner Eduardo "Eddie" Cantu to sign the approved change order. (ARPA-21-122-040)
BACKGROUND
Requesting 42 credit days due to weather and holidays. Requesting an additional 120 days to complete the project due to delays in materials and changes to the project. A total of 162 additional working calendar days. Resulting in a new contract expiration date of 12/26/2026. No fiscal impact.
Fiscal Impact
- CALENDAR YEAR:
- 2026
- ACCT. #:
- 1301-52-122-000-0000-507400
- FUNDS AVAILABLE Y/N?:
- Y/Pending
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
N/AAttachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | Ignacio Amezcua | 08/24/2026 03:23 PM |
| Budget and Management | Veronica Ortiz | 08/24/2026 03:38 PM |
| Final Approval | Monica Salinas | 08/26/2026 04:39 PM |
- Form Started By:
- Lupita Garza
- Started On:
- 08/24/2026 08:56 AM
- Final Approval Date:
- 08/26/2026