Information

CAPTION

Requesting approval of Change Order No. 2 (C-25-0169-05-13) with RBM Contractors, LLC for the Hidalgo County Precinct #2 — Recreational Trails Connectivity Project — McAllen Segment 1 (from Taylor Rd. to Ware Rd. and 23rd St. to 10th St.), as recommended by Project Manager Saul Ramos, with authority for Commissioner Eduardo "Eddie" Cantu to sign the approved change order. (ARPA-21-122-040)

BACKGROUND

Requesting 42 credit days due to weather and holidays.  Requesting an additional 120 days to complete the project due to delays in materials and changes to the project.  A total of 162 additional working calendar days.  Resulting in a new contract expiration date of 12/26/2026.  No fiscal impact.

Fiscal Impact

CALENDAR YEAR:
2026
ACCT. #:
1301-52-122-000-0000-507400
FUNDS AVAILABLE Y/N?:
Y/Pending
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

N/A

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal Ignacio Amezcua 08/24/2026 03:23 PM
Budget and Management Veronica Ortiz 08/24/2026 03:38 PM
Final Approval Monica Salinas 08/26/2026 04:39 PM
Form Started By:
Lupita Garza
Started On:
08/24/2026 08:56 AM
Final Approval Date:
08/26/2026