AI - 104657
6.I.
DD-REGULAR AGENDA SPECIAL MTG
Meeting Date:
09/15/2026
Submitted For:
Omar Anzaldua Jr.
Submitted By:
Justin Silva
Department:
DRAINAGE DISTRICT

Information

CAPTION

Requesting approval of Change Order No. 1, reflecting an increase of $52,856.92 and 95 additional construction calendar days for the project "North Main Drain Expansion - Phase II", Contract No. C-HCDD1-25-063-03-03, with Clore Equipment, LLC, as recommended by Project Engineer, Assistant District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM.