AI - 104753
8.A.
DD-REGULAR AGENDA REGULAR MTG
- Meeting Date:
- 09/22/2026
- Submitted By:
- Alvaro Chuc
- Department:
- DRAINAGE DISTRICT
CAPTION
Panchitas Outfall - Budget 706
1. Approval of Application for Payment No. 7 in the amount of $128,057.40 from Synergy Development & Construction pertaining to Construction Contract C-HCDD1-25-037-09-30. Project Engineer HCDD1 Omar Anzaldua, Jr. PE, CFM PO#651829
La Villa-Edcouch-Elsa Phase 2 - Budget 708
2. Approval of Application for Payment No. 8 in the amount of $163,502.81 from Construx Enterprises pertaining to Construction Contract C-HCDD1-25-036-07-22. Project Engineer S2 Engineering PO#651335
PD Lateral Extension 5 - Budget 715
3. Approval of Application for Payment No. 10 in the amount of $75,701.25 from Synergy Development & Construction pertaining to Construction Contract C-HCDD1-25-015-06-24. Project Engineer Izaguirre Engineering Group PO#651274
1. Approval of Application for Payment No. 7 in the amount of $128,057.40 from Synergy Development & Construction pertaining to Construction Contract C-HCDD1-25-037-09-30. Project Engineer HCDD1 Omar Anzaldua, Jr. PE, CFM PO#651829
La Villa-Edcouch-Elsa Phase 2 - Budget 708
2. Approval of Application for Payment No. 8 in the amount of $163,502.81 from Construx Enterprises pertaining to Construction Contract C-HCDD1-25-036-07-22. Project Engineer S2 Engineering PO#651335
PD Lateral Extension 5 - Budget 715
3. Approval of Application for Payment No. 10 in the amount of $75,701.25 from Synergy Development & Construction pertaining to Construction Contract C-HCDD1-25-015-06-24. Project Engineer Izaguirre Engineering Group PO#651274
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 09/16/2026 04:03 PM |
- Form Started By:
- Alvaro Chuc
- Started On:
- 09/16/2026 07:52 AM
- Final Approval Date:
- 09/16/2026