CAPTION
Presentation for consideration, discussion, acceptance and approval of Change Order No. 1 with contractor Jimmy Closner and Sons Construction for Eldora Gardens Subdivision located in Pct. No. 2 reflecting a net increase in the amount of $3,862.95 because concrete driveway was increased to have a better slope as recommended through project engineer R. Gutierrez Engineering Corporation. C-CAP 08-018-08-26.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2009
- ACCT. #:
- 9-1311-431-00-122-252-0-733
- FUNDS AVAILABLE Y/N?:
- Y/pending
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
P.O.# 619742 has available amount of $34,987.50; PO will need an increase.
Pending LIT on 5/26/09 AI-15560 for $3,862.95 for Change Order No.1
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 05/20/2009 02:09 PM |
| Budget and Management | Veronica Lopez | 05/20/2009 02:25 PM |
| Auditor's Office | 05/22/2009 05:22 PM |
- Form Started By:
- mjackson
- Started On:
- 05/18/2009 04:17 PM
- Final Approval Date:
- 05/22/2009