Request to approve project completion and final payment to Herrera & Hunt, Inc. pursuant to action taken on 04/14/09 and approval of Change Directive #1 authorizing contractor to use landscaping and betterment allowance for ADA compliance as required by Texas Parks & Wildlife Grant.  Approval requested for the following:

a. Change Directive #2 for installation of Solar Powered Lights; ADA Signage, Handrails and submission of Accessibility Study Reports, etc.

b. Change Order #1 is a quantitative adjustment reducing original amount of PO #606377 in the amount of $219,307.00 by $885.00 for a remaining balance of $218,422.00.

c. Approval of Contractor's Application for Final Payment #4 in the  amount of $25,615.90 which includes retainage payable to Herrera & Hunt, Inc. for Project #2008-119-OGG.

d. Approval and Acceptance of Certificate of Project Completion Form as provided by Texas Parks & Wildlife for Project F183B as identified by TPW Grant Funds.

BACKGROUND

Project #08-119-OGG has been completed; approval of proposed request will close-out Phase I of Improvements to Anzladua's Boat Ramp & Courtesy Dock Pct. #3.

Fiscal Impact

FISCAL YEAR:
2009
ACCT. #:
9-1287-452-00-123-043-9-739
FUNDS AVAILABLE Y/N?:
Y/Pending
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Pending P.O. Increase please refer to AI # 16526 (transfer of funds) on 7/21/09 CC in the amount of $5,000.00.

$ 5,000.00 [Transfer] $ 4,193.00
+$ 78.00 [Current P.O. Balance] + $21,422.90 [Retainage]
- $ 885.00 [Change Order #1] $25,615.90 [Total Final Payment]
$ 4,193.00 [New P.O. Balance]


FISCAL YEAR:
2009
ACCT. #:
9-1287-206-00-000-002-0-000
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Available funds in P.O. #606377 as of 7/24/09 is $21,422.90 for Retainage Payable.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 07/23/2009 03:20 PM
Budget and Management Erika Zamora 07/23/2009 04:20 PM
Auditor's Office 07/24/2009 05:10 PM
Form Started By:
Olga Garza
Started On:
07/22/2009 04:23 PM
Final Approval Date:
07/24/2009