Acceptance, and approval of Application for payment No. 3 (Release of Retainage) in the amount of $5,019.13 from Valley Paving Inc. contracted vendor for Dimas #1 Subdivision, submitted by project engineer TEDSI Infrastructure Group, CAP 08-033-3-31.

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2009
ACCT. #:
9-1311-206-00-000-019-0-000
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Project has been completed, P.O.# 621821 has been paid in full.

Available balance of retainage payable for Valley Paving, Inc. is $15,522.73 as of 8/28/09.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 08/27/2009 12:55 PM
Budget and Management Erika Zamora 08/27/2009 02:30 PM
Auditor's Office 08/28/2009 06:09 PM
Form Started By:
mjackson
Started On:
08/24/2009 04:12 PM
Final Approval Date:
08/28/2009