CAPTION

Requesting approval of the following with contracted vendor, Closner Construction Company. in connection with the construction of "Culvert Crossing & Drainage Improvements Project Mile 13N & Mile 6W" with contract #C-08-320B-01-20-PO #619358 as submitted/certified by project engineer, Dos Logistics Inc.;

a.  Final Pay Application-$31,753.65;
b.  Retainage Fee-$22,900.55;
c.  Substantial Completion with date of July 25, 2009;
d.  Certificate Of Construction Completion with date of September 2, 2009

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2009
ACCT. #:
9-1339-431-00-121-055-0-733
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Amount available in PO# 619358 $33,424.90 as of 9/11/09 for Closner Construction Co.
Note: $1,671.25 will be paid from this PO as it relates to the retainage payable. Total contract amount $458,010.90. Work has been completed as certified by engineer.


FISCAL YEAR:
2009
ACCT. #:
9-1339-206-00-000-001-0-000
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Amount available as of 9/10/09 $21,229.30 for Closner Construction retainage payable. Note: Total retainage fee is in the amount of $22,900.55 of which $1,671.25 will be paid out of PO#619358. Work has been completed as certified by engineer.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 09/10/2009 04:12 PM
Budget and Management Erika Zamora 09/10/2009 04:41 PM
Auditor's Office 09/11/2009 05:30 PM
Form Started By:
vgarcia
Started On:
09/10/2009 03:04 PM
Final Approval Date:
09/11/2009