AI- 17465
24.F.1.
CC REGULAR
Meeting Date:
09/29/2009
Submitted For:
Agapito Vargas
Submitted By:
Marcie Jackson, COLONIA ACCESS PROGRAM
Department:

Information

CAPTION

Acceptance and approval of Change Order No. 1 with contractor Valley Paving, Inc. for Las Milpas Subdivision, Pct. No. 2 reflecting a (decrease) in the amount of ($3,120.40) because of final quantitative adjustments as submitted through project engineer, R. Gutierrez Engineering Corporation-(C-CAP 09-178-06-23).

BACKGROUND

Contract amount after change order no.1 will be $192,010.15

Fiscal Impact

FISCAL YEAR:
9
ACCT. #:
9-1312-431-00-122-413-0-841
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Amount available in PO#627124 is $43,576.60 (obj.841) as of 09/24/09.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 09/24/2009 11:31 AM
Budget and Management Erika Zamora 09/24/2009 01:23 PM
Auditor's Office 09/25/2009 05:16 PM
Form Started By:
mjackson
Started On:
09/11/2009 01:48 PM
Final Approval Date: