AI- 17559
25.G.2.
CC REGULAR
- Meeting Date:
- 09/22/2009
- Submitted For:
- Agapito Vargas
- Submitted By:
- Marcie Jackson, COLONIA ACCESS PROGRAM
- Department:
Information
CAPTION
Presentation for consideration, discussion, acceptance and approval of Change Order No. 2 with contractor Total Commitment, LLC for Los Encinos No. 1 and Los Encinos II Subdivisions, Pct. No. 2 reflecting a net increase in the amount of $4,704.00 due to reinstating installation of two street entrance culverts, and 14 calendar days added, as submitted through project engineer Izaguirre Engineering Group, LLC - C-CAP-09-128-05-05
BACKGROUND
New contract amount after change order will be $192,360.95
Fiscal Impact
- FISCAL YEAR:
- 9
- ACCT. #:
- 9-1312-431-00-122-89X-073X
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Ref: P.O.# 6273829-1312-431-00-122-890-0-731 - available balance is $ 3,126.41
9-1312-431-00-122-890-0-733 - available balance is $13,736.49
9-1312-431-00-122-891-0-731 - available balance is $ 81,05.44
9-1312-431-00-122-891-0-733 - available balance is $19,466.30
as of 09/18/09.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 09/17/2009 01:18 PM |
| Budget and Management | Erika Zamora | 09/17/2009 01:24 PM |
| Auditor's Office | lfong | 09/18/2009 01:06 PM |
- Form Started By:
- mjackson
- Started On:
- 09/16/2009 04:04 PM
- Final Approval Date:
- 09/18/2009