AI- 18151
26.G.1.
CC REGULAR
Meeting Date:
11/10/2009
Submitted For:
Agapito Vargas
Submitted By:
Marcie Jackson, COLONIA ACCESS PROGRAM
Department:

Information

CAPTION

Acceptance and approval of Change Order No. 1 with contractor Closner Construction Co. LC for Citriana Village Subdivision, Pct. No. 2 reflecting a request for an increase of 13 construction days due to rain and wet days as reviewed and submitted through project engineer Cruz-Hogan Consultants, Inc. (C-CAP 2009-183-05-19)

BACKGROUND

Contract amount remains at $322,888.69

Fiscal Impact

FISCAL YEAR:
9
ACCT. #:
9-1312-431-00-122-154-0-733/841
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Reference: P.O.#630113

*13 days are requesting to be added to contract due to weather related issues - no additional costs.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 11/05/2009 04:01 PM
Budget and Management Erika Zamora 11/05/2009 04:09 PM
Auditor's Office 11/06/2009 05:33 PM
Form Started By:
mjackson
Started On:
10/21/2009 03:47 PM
Final Approval Date:
11/06/2009