AI- 19816
27.D.1.
CC REGULAR
Meeting Date:
02/23/2010
Submitted For:
Agapito Vargas
Submitted By:
Marcie Jackson, COLONIA ACCESS PROGRAM
Department:

CAPTION

Approval of Application for Payment No. 3 (Final) in the amount of $47,248.65 from Total Commitment, LLC contracted vendor for Basham Subdivision No. 18 as submitted by Javier Hinojosa Engineering project engineer. (C-CAP-09-286-08-25)

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2010
ACCT. #:
0-1312-431-00-123-082-0-731/733
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Available funds in P.O. #630130 as of 2/19/10 is $53,974.00.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 02/19/2010 02:27 PM
Budget and Management Erika Zamora 02/19/2010 02:39 PM
Auditor's Office 02/19/2010 05:16 PM
Form Started By:
mjackson
Started On:
02/05/2010 11:49 AM
Final Approval Date:
02/19/2010