AI- 23619
27.B.4.
CC REGULAR
- Meeting Date:
- 10/26/2010
- Submitted For:
- Yolanda Cisneros
- Submitted By:
- Yolanda Cisneros, COMM. PCT. #2
- Department:
- COMM. PCT. #2
Information
CAPTION
Requesting approval of Change Order No. 2 increase in of 18 calendar day with Total Commitment LLC(contracted vendor for “North Tower Road Crossing Drainage Improvement Project”) reflecting weather days, due to recent rains, ground conditions too wet to conduct work within the project area, with authority for County Judge to execute document.
BACKGROUND
Contract #C-10-032-02-16 PO #637386
Fiscal Impact
- FISCAL YEAR:
- 2010
- ACCT. #:
- 0-1339-431-00-122-050-0-733
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
*only calendar days have increased to a total of 155 calendar days. Contract Amount has not changed.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 10/22/2010 11:31 AM |
| Budget and Management | Sylvia Solis | 10/22/2010 01:06 PM |
| Auditor's Office | lfong | 10/22/2010 02:48 PM |
- Form Started By:
- ycisneros
- Started On:
- 10/21/2010 01:36 PM
- Final Approval Date:
- 10/22/2010