CAPTION
Requesting approval of Change Order No. 1 (increase) in connection with "Primavera #1 Subdivision" in the amount of $7,941.00 from JM Construction, as recommended by project engineer R. Gutierrez Engineering Corp, and with authority for County Judge to execute document; C-CAP-06-005-11-28
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2007
- ACCT. #:
- 7-1311-431-00-122-568-0-734
- FUNDS AVAILABLE Y/N?:
- y
- MATCHING FUNDS Y/N?:
- n
BUDGETARY IMPACT:
Avail. Bal. $87,920.76- FISCAL YEAR:
- 2007
- ACCT. #:
- 7-1311-431-00-122-568-0-733
- FUNDS AVAILABLE Y/N?:
- y
- MATCHING FUNDS Y/N?:
- n
BUDGETARY IMPACT:
Avail. Bal. $51,636.00
- FISCAL YEAR:
- 2007
- ACCT. #:
- 7-1202-431-00-122-006-0-734
- FUNDS AVAILABLE Y/N?:
- y
- MATCHING FUNDS Y/N?:
- n
BUDGETARY IMPACT:
Agenda Item 2415 is a transfer to pay the remainder of the change orderAttachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 02/08/2007 01:45 PM |
| Budget and Management | Dina Trevino | 02/08/2007 04:40 PM |
| Auditor's Office | bmorales | 02/12/2007 02:39 PM |
| Mike Escaname | Mike Escaname | 02/16/2007 03:28 PM |
| Court Administrator | Monica Salinas | 02/23/2007 04:39 PM |
- Form Started By:
- Rocio Villarreal
- Started On:
- 02/07/2007 02:19 PM
- Final Approval Date:
- 02/23/2007