CAPTION

a. Approval of Change Order No 2 an increase of $58,831.30.00 and additional 44 days to the contract with D. Wilson Construction Co. (Contract #C-09-037-11-17) for the Construction of the New Pct 2 Administration & Other County Offices Complex" in connection with  all labor, equipment and materials for the work described including, but not limited to, change requests and other items;
b. Approval and/or ratification (whichever is applicable) of Architect's Supplemental Instructions No 15 (funded from the Allowances/Contingency) in the amount of $52,979.70, to contractor D. Wilson Construction Co., in connection with the "Construction of New Pct 2 Administration & Other County Offices Complex"-C-09-037C-11-17. 

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2010
ACCT. #:
Various Accounts
FUNDS AVAILABLE Y/N?:
Yes
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Funding is available through CO's Series 2002, 2004, and 2006.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 01/07/2011 04:13 PM