CAPTION
a. Approval of Change Order No 2 an increase of $58,831.30.00 and additional 44 days to the contract with D. Wilson Construction Co. (Contract #C-09-037-11-17) for the Construction of the New Pct 2 Administration & Other County Offices Complex" in connection with all labor, equipment and materials for the work described including, but not limited to, change requests and other items;
b. Approval and/or ratification (whichever is applicable) of Architect's Supplemental Instructions No 15 (funded from the Allowances/Contingency) in the amount of $52,979.70, to contractor D. Wilson Construction Co., in connection with the "Construction of New Pct 2 Administration & Other County Offices Complex"-C-09-037C-11-17.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2010
- ACCT. #:
- Various Accounts
- FUNDS AVAILABLE Y/N?:
- Yes
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Funding is available through CO's Series 2002, 2004, and 2006.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 01/07/2011 04:13 PM |
| Budget and Management | Erika Zamora | 01/07/2011 04:17 PM |
| Auditor's Office | 01/07/2011 06:02 PM |
- Form Started By:
- ycisneros
- Started On:
- 01/06/2011 07:50 PM
- Final Approval Date:
- 01/07/2011