CAPTION
Approval of:
1. Application for Payment No. 3 (Retainage Release) in the amount of $27,421.65;
2. “Certificate of Construction Completion” reflecting the completion date of November 15, 2010;
from M Construction, LTD for Chapa II Subdivision as reviewed and submitted by project engineer Izaguirre Engineering Group (C-CAP 09-372-11-24).
1. Application for Payment No. 3 (Retainage Release) in the amount of $27,421.65;
2. “Certificate of Construction Completion” reflecting the completion date of November 15, 2010;
from M Construction, LTD for Chapa II Subdivision as reviewed and submitted by project engineer Izaguirre Engineering Group (C-CAP 09-372-11-24).
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2011
- ACCT. #:
- 1-1312-206-00-000-013-0-000
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
P.O.# 641490 for M Construction in relation to Chapa #2 has been paid in full; total contract amount is $274,216.48"Retainage Payable-M Construction-Pct. 1"-Available balance as of 2-17-11 $27,421.65
Attachments
- Application for Payment No.3 Retainage Release Chapa II Subdivision
- Certificate of Construction Completion Chapa No.2 Subdivision
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 02/16/2011 01:21 PM |
| Budget and Management | Erika Zamora | 02/16/2011 03:00 PM |
| Auditor's Office | lfong | 02/17/2011 05:12 PM |
- Form Started By:
- mjackson
- Started On:
- 02/04/2011 02:08 PM
- Final Approval Date:
- 02/17/2011