A. Request approval of Payment Request No. 18 to SER Construction Partners, LTD. for the Construction of DHS 0-7 (0.90 miles).
B. Request approval to process manual check to SER Construction Partners, LTD. for the above mentioned project pending the approval of the County Auditor and Department of Homeland Security (DHS) and pending the electronic transfer of funds from the Department of Payment Management (DPM).
C. Request approval of Change Order No. 44 and No. 45 on the Contract with SER Construction Partners, LTD. for the Construction of Levee DHS 0-6BC. Subject to Department of Homeland Security (DHS) concurrence.
B. Request approval to process manual check to SER Construction Partners, LTD. for the above mentioned project pending the approval of the County Auditor and Department of Homeland Security (DHS) and pending the electronic transfer of funds from the Department of Payment Management (DPM).
C. Request approval of Change Order No. 44 and No. 45 on the Contract with SER Construction Partners, LTD. for the Construction of Levee DHS 0-6BC. Subject to Department of Homeland Security (DHS) concurrence.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Erika Zamora | 03/23/2011 11:51 AM |
| Final Approval | 03/25/2011 07:31 AM |
- Form Started By:
- mluna
- Started On:
- 03/21/2011 09:04 AM
- Final Approval Date:
- 03/25/2011