AI- 30364
13.B.2.
CC REGULAR
- Meeting Date:
- 01/10/2012
- Submitted For:
- Yoli Cisneos
- Submitted By:
- Yolanda Cisneros, COMM. PCT. #2
- Department:
- COMM. PCT. #2
Information
CAPTION
Requesting approval of Construction Change Order No. 2 increase the amount of days for 55 calendar days with Mission Paving Company, Inc. (Contracted vendor for "Tower Road Phase I Project" reflecting 1) unable to start work due to fiber optic line not relocated by utility company, with authority for County Judge to execute document.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2011
- ACCT. #:
- 1-1200-431-00-122-049-0-731
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
PO #662859 available balance of $225,690.90 (with increase of $17,000) as of 12/28/2011.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 12/28/2011 05:03 PM |
| Budget and Management | mmunoz | 12/29/2011 08:11 AM |
| Auditor's Office | Alejandro Garcia | 12/29/2011 04:59 PM |
- Form Started By:
- ycisneros
- Started On:
- 12/28/2011 04:22 PM
- Final Approval Date:
- 12/29/2011