Skip to main content

AgendaQuick™

View Agenda Item

AI- 35020
7.I.
CC CONSENT
Meeting Date:
11/13/2012
Submitted For:
Agapito Vargas
Submitted By:
Marcie Jackson, COLONIA ACCESS PROGRAM
Department:

Information

CAPTION

Presentation for consideration, discussion, acceptance and approval of the following items with GP7 Construction, LLC contracted vendor for La Homa Road South Subdivision, Pct. No. 3 as submitted through project engineer, Javier Hinojosa Engineering. (C-CAP-12-090-05-29):

1. Application for payment No. 3 (Retainage) in the amount of $16,340.22;
2. “Certificate of Construction Completion” reflecting the date of September 28, 2012.

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2012
ACCT. #:
2-1312-206-00-000-032-0-000
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Available funds in P.O. #678538 as of 11/08/12 for retainage payable are $16,340.22.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 11/07/2012 04:37 PM
Budget and Management mmunoz 11/07/2012 04:48 PM
Auditor's Office Alejandro Garcia 11/09/2012 03:32 PM
Form Started By:
mjackson
Started On:
10/30/2012 10:38 AM
Final Approval Date:
11/09/2012