CAPTION

Approval of request for payment Application No. 2 in the amount of $ 68,668.48 from Rigney Construction contracted vendor for: Interior Repairs and Renovations 398th. District Court" contract No. C-06-176-01-29 PO No. 580665 and as certified for payment by project architect, AGADC contract No. C-06-177-04-11 PO No. 570477.        (6-176)

BACKGROUND

Memorandum to  Daniel Flores B&G Director
Application and Certificate for payment  No. 2

Fiscal Impact

FISCAL YEAR:
2007
ACCT. #:
7-1334-412-40-220-010-0-452
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

$79,156.72 P.O. available balance as of 04-25-07. RC

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 04/21/2007 10:45 AM
Budget and Management Dina Trevino 04/25/2007 09:07 AM
Auditor's Office bmorales 04/30/2007 09:00 AM
Court Administrator Monica Salinas 05/17/2007 05:24 PM
Form Started By:
jtapia
Started On:
04/20/2007 02:59 PM
Final Approval Date:
05/17/2007