AI - 41551
4.
DRAINAGE - CONSENT
- Meeting Date:
- 11/12/2013
- Submitted By:
- Sylvia Sanchez, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
2013 Bond Series
Approval of invoice #3408, WA#1 for R. Gutierrez Engineering Corp. as it relates to Alamo Exp Drain/South Floodwater Channel in the amount of $96.188.24, PO#622584.
Approval of invoice #3408, WA#1 for R. Gutierrez Engineering Corp. as it relates to Alamo Exp Drain/South Floodwater Channel in the amount of $96.188.24, PO#622584.
BACKGROUND
Fiscal Impact
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Obdett Calzada | 10/30/2013 04:00 PM |
| Final Approval | Monica Salinas | 11/08/2013 04:34 PM |
- Form Started By:
- ssanchez
- Started On:
- 10/30/2013 02:37 PM
- Final Approval Date:
- 11/08/2013