Seeking ratification of fully executed Change Order No. 1 reflecting an additional 21 calendar days due to rain days with contractor Castle Enterprises, LLC for Randolph Barnett #1 Subdivision, Pct. No. 3 as submitted though project engineer Javier Hinojosa Engineering (C-CAP-13-191-07-30).

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2014
ACCT. #:
4-1312-431-00-123-600-0-733/731
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

No Fiscal Impact.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 02/26/2014 02:07 PM
Budget and Management Debbie Tamez 02/26/2014 02:50 PM
Auditor's Office Monica Salinas 02/28/2014 05:19 PM
Form Started By:
mjackson
Started On:
02/19/2014 03:13 PM
Final Approval Date:
02/28/2014